Grounding, Bonding, and Electrical Safety Under the NEC

National Electrical Code

Published on November 19, 2026 by Staff Writer

Yellow electrical conduits and green grounding cables are secured to metal mounting rails along a concrete wall.

In the 2023 National Electrical Code (NEC), NEC Article 250 sets the requirements for grounding and bonding electrical systems. The National Fire Protection Association (NFPA) publishes the code as NFPA 70.

These requirements cover grounding systems and equipment, installing grounding electrodes, and making the bonding connections that help protective devices operate during a ground fault.

Why Electrical Systems Are Grounded to Earth

Under NEC 250.4(A)(1), the connection to earth limits how high the system voltage can rise because of lightning, line surges, or accidental contact with a higher-voltage line. This helps protect electrical equipment. The connection also stabilizes the voltage relative to earth during normal operation.

NEC 250.4(A)(5) excludes the earth as an effective ground-fault current path. During a ground fault, a bonded low-impedance path carries fault current back to the electrical supply source so the protective device can operate.

Which NEC Article Covers Grounding and Bonding?

Article 250 covers grounding and bonding. The foundational requirements appear in Part I, which includes Section 250.4. Later parts address specific applications, including system grounding, grounding electrode installation, equipment grounding, and direct-current systems. For training on these requirements, see JADE Learning’s NEC courses.

Pro-tip: During routine inspection and testing, verify that the equipment grounding conductors, bonding jumpers, and panel connections are intact and electrically continuous. A continuous, low-impedance path helps the breaker or fuse operate promptly during a ground fault. In general industry, OSHA’s grounding-path rule, 29 CFR 1910.304(g)(5), requires a permanent, continuous, and effective path.

Permitted Methods for Grounding and Bonding Connections

Section 250.8(A) covers connections for equipment grounding conductors, grounding electrode conductors, and bonding jumpers. Use one or more of the designated methods in the table for these connections. NEC 250.8(B) prohibits connection devices or fittings that depend solely on solder.

Permitted Method

Description

Listed pressure connectors — 250.8(A)(1)

Pressure connectors with a listing that covers the intended application.

Terminal bars — 250.8(A)(2)

Bars with terminals for conductor connections.

Pressure connectors listed as grounding and bonding equipment — 250.8(A)(3)

Pressure connectors specifically listed for grounding and bonding.

Exothermic welding — 250.8(A)(4)

A chemical reaction generates the heat that welds the parts together.

Machine screw-type fasteners — 250.8(A)(5)

The fastener must engage at least two threads or be secured with a nut.

Thread-forming machine screws — 250.8(A)(6)

The screw must engage at least two threads in the enclosure.

Connections within a listed assembly — 250.8(A)(7)

The connection is part of an assembly covered by a listing.

Other listed means — 250.8(A)(8)

Other connection methods covered by a listing from a product evaluation organization acceptable to the authority having jurisdiction. The listing confirms compliance with the applicable standard or suitability for the specified use.

Common Grounding Electrodes and Their Installation Requirements

The following are common electrode types. NFPA provides a broader overview of the grounding electrode system.

Metal Underground Water Pipe

The pipe must have at least 10 feet of direct contact with the earth and be electrically continuous to the connection points. It also requires a supplemental electrode of a type permitted by NEC 250.53(D)(2). See NEC 250.52(A)(1) and 250.53(D)(2).

Metal In-Ground Support Structures

A metal in-ground support structure must extend at least 10 feet vertically in contact with the earth, with or without concrete encasement, to qualify under NEC 250.52(A)(2). For a metal building frame, NEC 250.68(C)(2) separately permits a connection to a qualifying concrete-encased electrode through properly connected steel column hold-down bolts.

Concrete-Encased Electrode (Ufer Ground)

Use at least 20 feet of bare copper conductor sized 4 American Wire Gauge (AWG) or larger, or at least 20 feet of qualifying steel reinforcing bar at least ½ inch in diameter. The electrode must have at least 2 inches of concrete cover in a qualifying foundation, footing, or structural member in direct contact with the earth. See NEC 250.52(A)(3).

Ground Ring

A ground ring uses at least 20 feet of bare copper conductor sized 2 AWG or larger. It must encircle the building or structure, contact the earth directly, and be buried at least 30 inches below the surface. See NEC 250.52(A)(4) and 250.53(F).

Rod and Pipe Electrodes

Rod and pipe electrodes must be at least 8 feet long, with at least 8 feet in contact with the soil. NEC 250.53(A)(4) permits angled driving when you encounter rock bottom and trench installation when the code’s conditions for that option are met.

A single rod or pipe electrode with a resistance to ground of 25 ohms or less qualifies for an exception to the supplemental-electrode requirement. See NEC 250.52(A)(5) and 250.53(A)(2) and (4).

Plate Electrodes

A plate electrode must expose at least 2 square feet of surface to the surrounding soil and be buried at least 30 inches below the surface. The same 25-ohm exception to the supplemental-electrode requirement applies to a single plate electrode. See NEC 250.52(A)(7) and 250.53(A)(2) and (5).

Bonding the Grounding Electrodes

NEC 250.50 requires the electrodes described in 250.52(A)(1) through (A)(7) that are present at a building or structure to be bonded together into a single grounding electrode system. An exception applies to a concrete-encased electrode in an existing building or structure if accessing the reinforcing bar would require disturbing the concrete.

What Is the Purpose of Bonding Metal Parts?

Bonding permanently connects normally non-current-carrying metal parts, such as enclosures, raceways, and equipment, to establish electrical continuity. If an energized conductor touches a bonded metal enclosure, the effective ground-fault current path allows enough current to flow back to the supply source to operate a breaker or fuse and disconnect the faulted circuit.

Effective Ground-Fault Current Path

For grounded systems, NEC 250.4 specifies in (A)(3) and (4) which conductive parts must be bonded together and connected to the supply source. NEC 250.4(A)(5) requires a low-impedance path capable of safely carrying the maximum ground-fault current likely to occur.

Components and Methods

Equipment grounding conductors, bonding jumpers, and properly installed metal raceways and enclosures can form parts of the bonded path. The permitted means depend on the installation.

Distinction from Grounding

In electrical safety, grounding and bonding serve different but complementary roles. An installation can have a grounding electrode in place even if a bond at a metal enclosure is incomplete. Checking the enclosure’s bonding connection helps verify that fault current has a continuous path back to the supply source.

Parts of Article 250 (2023 NEC)

The 2023 NEC organizes Article 250 into these 10 parts.

Part

Title

I

General

II

System Grounding

III

Grounding Electrode System and Grounding Electrode Conductor

IV

Enclosure, Raceway, and Service Cable Connections

V

Bonding

VI

Equipment Grounding and Equipment Grounding Conductors

VII

Methods of Equipment Grounding Conductor Connections

VIII

Direct-Current Systems

IX

Instruments, Meters, and Relays

X

Grounding of Systems and Circuits of over 1000 Volts

In the 2026 NEC, Article 250 has nine parts and covers installations rated up to 1,000 volts AC or 1,500 volts DC, nominal. The requirements for grounding systems over 1000 volts formerly in Part X moved to Article 270. Check which NEC edition your state or local jurisdiction has adopted before applying a section reference.